Stanley-1 Well Test Results

 

 

Mosman Oil and Gas Limited (AIM: MSMN) the oil exploration, development and production company, announces an update in respect to a recently completed well test at the Stanley-1 well.

 

A well test was recently performed on Stanley-1 to ascertain the potential deliverability of the well. The test was carried out by the operator, Nadsoilco LLC, and independent third parties. This was a controlled test designed to flow the well with gas flared (instead of producing to the restricted gas infrastructure) and to acquire data that may indicate the extent of the oil and gas accumulation. The test rate was limited due to the size of the test separator and was not an absolute open hole test. Over several hours the well was flowed through increasingly larger choke sizes and the flow rate was allowed to stabilise at each stage.

 

The choke was incrementally increased from 11/64" to 40/64" over a series of steps and the final stable flow was 1,271,000 cfd and 50 bbls per day of liquid hydrocarbons. This is equivalent to 274 boepd (calculated using SPE conversion rate of 0.0001767 barrels per standard cubic foot of gas). By way of comparison, recent  flow rates with  existing infrastructure  were averaging 450,000 cfd  and 10  bbls per day of liquid hydrocarbons. This is equivalent to 90 boepd. Figures stated as gross to the project with Mosman holding a 16.5% Working Interest.  

 

The operator has advised that planning and negotiating with relevant parties to eliminate pipeline limitations and increase gas processing contract volumes is underway.   The timing of increased production depends on reaching agreement with third parties and completing site work, and an update will be provided in due course.

 

The Stanley-2 well drill is scheduled to commence drilling in November with results due in early December. The well is expected to be an oil producer with minor amounts of associated gas that can be handled by existing infrastructure.

 

Additional development wells will then be drilled to develop the multiple oil zones identified in Stanley-1.

 

John W Barr, Chairman, said: 

"This Stanley-1 test shows the ability of the well to produce at much higher rates once the gas infrastructure limitations are resolved. We are also pleased to move rapidly to drill Stanley-2 and potentially get it on production, to be followed by additional wells.

Stanley-1 continues to generate revenue from gas and oil sales, and the test clearly shows the potential for higher rates once the current gas constraints are removed."

Competent Person's Statement

The information contained in this announcement has been reviewed and approved by Andy Carroll, Technical Director for Mosman, who has over 35 years of relevant experience in the oil industry. Mr. Carroll is a member of the Society of Petroleum Engineers.

 

 

Market Abuse Regulation (MAR) Disclosure

Certain information contained in this announcement would have been deemed inside information for the purposes of Article 7 of Regulation (EU) No 596/2014 until the release of this announcement.

 

 

 Enquiries:

 

Mosman Oil & Gas Limited

John W Barr, Executive Chairman

Andy Carroll, Technical Director

jwbarr@mosmanoilandgas.com

acarroll@mosmanoilandgas.com

 

NOMAD and Broker

SP Angel Corporate Finance LLP

Stuart Gledhill / Richard Hail / Soltan Tagiev

+44 (0) 20 3470 0470

 

Gable Communications Limited

Justine James / John Bick

+44 (0) 20 7193 7463

mosman@gablecommunications.com

Joint Broker

SVS Securities Plc

Tom Curran / Ben Tadd

+44 (0) 203 700 0078

 

Updates on the Company's activities are regularly posted on its website www.mosmanoilandgas.com

 

 

 

APPENDIX 1

Glossary of Oil and Gas Terms

 

             

bbl

Barrel

bpd

Barrels Per Day (Liquids)

bopd

Barrels of Oil Per Day

M

Thousand

MM

Million

boe

Barrel of Oil Equivalent

boepd

Barrel of Oil Equivalent per day

(calculated using SPE conversion rate of 0.0001767)

scf

Standard Cubic Feet

Mscf

Thousand Standard Cubic Feet

 

 


This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
MSCFFLSADFASEIF